G&S Action Items

From Deep Thought

Jump to: navigation, search

Contents

Action Items

All of these items are still outstanding as of 05/01/2008 at 10PM EST.

General (All Rooms)

Many items listed here are problems that are found in every room, i.e. outlet & switch issues. We only list them once, but every room needs to be reviewed.

  1. Deadbolt locks on exterior doors, matching keys
  2. Switches & Outlets
    1. Square & level & PROPERLY INSTALL all switches and outlets
    2. Install all outlet & switch covers
  3. Fire alarms : remove pull tabs
  4. Clean Up
    1. Generator and other construction materials in garage

Green BR (Nicolas Room)

  1. Door doesn't latch shut
  2. Low spot on left wall (bathroom wall)
  3. Buckling @ door

Blue BR (Office)

  1. Dents in floor in front of window
  2. Patch/paint under outlet on right side (behind door)

Front Hall

  1. Patch to left of thermostat
  2. Clean thermostat
  3. Re-install cover to attic crawl space
  4. Patch back wall in coat closet & paint
  5. Fix paint run on coat closet trim (left side @ door latch)

Small Bath

  1. Clean light fixtures
  2. Replace toilet seat

Foyer

  1. Clean garage threshold
  2. Clean main doorway threshold

Garage

  1. Clean popcorn off light fixture
  2. Clean popcorn off fridge
  3. Paint threshold support

Living Room

  1. Remove incorrectly placed cable outlet
  2. Fix window to right of fireplace, lock is damaged
  3. Patch around outlet on kitchen full wall
  4. Patch around both switches on left of fireplace
  5. Fix paint run under counter @ full/half wall intersection
  6. Refinish/paint end of half wall
  7. Fix paint run top left of fireplace
  8. Fix fireplace cabinet caulking on right side
  9. Lower ceiling fan (rod is on site)
  10. Replace scratched floor 6' out from center of fireplace

Kitchen

  1. Half wall @ dishwasher needs paint or trim
  2. Patch wall to left of cabinets near half-wall
  3. Plumb dishwasher

Master Hall

Laundry Room

  1. Paint right wall

Master BR

  1. Clean threshold @ french doors
  2. Fix french door latching
    1. bottom left pin not seating
    2. right door not latching with left side


Master Bath

  1. Install base & shoe molding
  2. Install shower surround: frameless glass enclosure
  3. Sand & Paint wall to right of toilet @ start of half wall
  4. Install drain stop & lever in tub

Master Closet

  1. Patch ceiling

Attic

  1. Replace all insulation where needed. Known issues:
    1. top of pulldown in garage above electric box
    2. top of pulldown, foyer wall
    3. above living room, kitchen side

Exterior

  1. Replace cable going into office,sheathing was cut when siding was installed
  2. Re-attach cable to splitter
  3. Mount cable splitter to side of house
  4. Replace siding as necessary on HVAC side after removing exterior conduit
  5. Paint threshold support under french doors (white)
  6. Fix drain pipe for HVAC blower overflow
  7. Clean all screens
  8. Paint mailbox (scratched from trailer)
  9. Clean rust stains on back patio tile (from nails, etc.)
  10. Repair broken tile on edge of patio (from cutting concrete)
  11. Lawn to left of driveway needs to be filled & seed from POD & trailers
  12. Driveway needs to be washed/rust stains from trailer removed
  13. Sod lawn on front right corner where painters have been dumping paint, cleaning brushes, etc.

Misc

  1. Delivery of remote & instructions for living room ceiling fan
  2. Test remote for master BR ceiling fan (was remote receiver installed)?
  3. Need a copy of letter from Glenn Zuber citing foundation is OK to build on
  4. Need copy of any correspondence sent from G&S to Town of Mt Pleasant re: foundation
  5. Copy of permits & inspections
  6. Removal of POD, we require a weekend after garage is finished to unload

Repairs To Be Made

  1. Washer/Dryer door bezel needs to be replaced, I have a quote from repair shop ($120 est. + $100 site visit fee)
  2. Washer/Dryer sides cannot be replaced, may be able to repair
  3. Light fixture in dining nook damaged, plaster was removed along with the finish. ($300 fixture)
  4. Far left cabinet has ding on front, was not there after cabinets or appliances were installed, new door needs to be ordered if it can't be repaired.